Thursday, July 7, 2011 | The California High-Speed Rail Authority is in serious danger of starting a massive construction project that it may be unable to finish, according to a detailed assessment by its Peer Review Group.
And if it does begin building the 800-mile train system next year as scheduled, its overall plan is skewed, according to the nine-page report, because whoever will operate the train system should be closely involved in major construction decisions. The Rail Authority doesn’t have a plan for operating the train system or who will run it.
In addition, the report said no commitments should be made to begin construction “until the Legislature and Governor have made an expedited review of the 2011 Business Plan and agreed on a course of action.” The business plan is due Oct. 1 but has run into management problems.
These were among a number of other issues raised by the report, including who will own and operate the trains and how much the project may actually cost. It is the most detailed report yet on potential problems with building the train system.
Like This Free Civic News? Support Voice of OC Today.
The eight-member committee, headed by Will Kempton, chief executive of the Orange County Transportation Authority, is composed of outside transportation experts appointed to conduct reviews of the proposed rail project.
The group’s latest assessment, sent July 1 to the High-Speed Rail Authority and top staff as well as key lawmakers, was compiled at the request of the state Senate’s Select Committee on High-Speed Rail.
“Neither the State nor the Federal Government has given any guarantee of future funding beyond the amounts already allocated,” the report reminded lawmakers. “This poses the clear risk that whatever is started will not be finished and whatever is finished may have only limited utility.
“In any event,” it continued, “the State may be faced with a limited utility project (albeit partly funded with federal grants) or may need to decide to complete the project using only its own resources if there is no further Federal funding.”
Federal rail officials and the Rail Authority have agreed to begin construction in the Central Valley by next year in order to qualify for federal stimulus funds. Projects using those funds must be finished in five years. The total cost now is estimated at $43 billion to $65 billion.
But critics worry the project will become a “train to nowhere” if money isn’t found to take it beyond the valley. And the approval given by voters in 2008 for the project specified that no tax money can be used to run it, once it is completed.
In its report, the Peer Review Group warned “there are no risk free ‘mega-projects.’ None.”
“Whatever else is accomplished before construction commitments begin,” it emphasized, “it is essential that major risks be defined, clarified, understood, allocated and accepted to the degree possible.”
The report recommended changing the management structure for construction of the rail system but said the best way to do that can’t be determined until there is a business plan.
And it said current project leaders may have their scheduling backwards, making critical decisions before they know who will be operating the system. The operator could be a private company, a government agency or some sort of hybrid.
“The importance of the operator’s input into the details of the systems design cannot be overstated,” the report said. “… Consequently, it is the norm to let a concession contract for the operator several years prior to the start of commercial operations and before many critical engineering decisions are made.”
The peer group report warned that the way the project is progressing, the state, not the ultimate operator, could be liable for future safety problems.
“These are not abstract problems for which the answers can be delayed for the present and then allowed to emerge over the years,” the report said.
Neither Kempton nor Sen. Alan Lowenthal (D-Long Beach), chairman of the Select Committee on High-Speed Rail could be reached for comment Wednesday.
Numerous Unfavorable Reports
The Peer Review Group report is the latest in a string of unfavorable reports released over the past two years on the high-speed rail project, which was approved by voters in 2008.
Among other things, state audits determined thst millions of dollars were paid to subcontractors without invoices and that ridership estimates necessary to attract private investors are faulty. Rail contractors and project leaders have been criticized by community leaders and farm owners along the planned route for brushing them aside and failing to communicate openly about the project.
One of the most recent reports was done in May by the state’s Legislative Analyst’s Office.
The report urged the Legislature to quickly take control of the fledgling train system and turn it over to Caltrans.
The Rail Authority, in its response to the legislative analyst, said the rail project “has been successful to date in large part because the Authority is not buried within the state bureaucracy.”
Rail Authority CEO Roelof van Ark wrote in a letter to the Senate committee that “after taking a thorough look at this report, we however see many flaws in its analysis and can say with certainty that if the Legislature were to adopt the recommendations made by the [legislative analyst], it would effectively end the largest infrastructure project in our state’s history and would turn back nearly $4 billion in federal funding …”
The Rail Authority is under pressure from Washington to begin construction by next year or lose the $4 billion in federal stimulus funds referred to by Roelof. At the recommendation of the legislative analyst, it asked about extending the deadline, but federal rail officials said they didn’t have the authority to make an exception for California.
According to a posting on the High-Speed Rail Authority’s website, for at least a decade — even before voters in 2008 approved $9 billion to begin construction of the Anaheim-to-San Francisco train system — the Rail Authority has been planning how to build the project.
“Over the last 10 years,” it says, “the Authority has carefully and extensively done the studies necessary to prepare for the implementation of high-speed trains in California.”
But the latest Peer Review Group report, which was written to respond to the legislative analyst’s review, said it agreed that “the project is truly at a ‘Critical Juncture’ posing perhaps the last available opportunity for the Legislature and Governor to ensure the project is on the right course before a commitment to construction is irrevocable.”
But it didn’t endorse the idea that Caltrans should take over, saying the project was too big for either Caltrans or the current rail authority.
And among the many issues it raised, the Peer Review Group once again urged lawmakers to ensure that the Rail Authority adopts a basic business plan by its October deadline.
“In previous letters we have highlighted this critical issue,” the Peer Group report said, “because the business model brings together the sources of money, allocation of costs and benefits, and apportionment of risks.”
But just this week an analysis by the staff of the Senate Transportation and Housing Committee of separate rail-related legislation disclosed that the Rail Authority was months off-track in its work to develop such a model.
Please contact Tracy Wood directly at twood@voiceofoc.org and follow her on Twitter: twitter.com/tracy111. And add your voice with a letter to the editor.